In TPP „Kolubara", Unit A-5, in Veliki Crljeni
New ash handling system was commissioned - In Thermal Power Plant „Kolubara" inVeliki Crljeni, the oldest thermal capacity CE TENT and PE EPS...
New ash handling system was commissioned - In Thermal Power Plant „Kolubara" inVeliki Crljeni, the oldest thermal capacity CE TENT and PE EPS...
Revitalization of the Unit TENT А5 starts on 1 June and will last until 30 September 2012, it was said at the meeting of the main...
„The major overhaul" started on 7 April - Within this year overhaul activities (180 days) the replacement of 70.000 welded joints was envisiged...
Corporate Enterprise "Thermal Power Plants Nikola Tesla" produced and distributed to Electric Power System, 1.544.234.000 kWh...
Successful in the first quarter - Railway Transport of the Corporate Enterprise TENT has finished the first quarter of the ongoing year very successfully.